Rushcliffe expects to finish 2026/27 £1.056m under budget, mainly from interest on its cash. Most would go to reserves, with £300,000 for town improvements.

Rushcliffe Borough Council expects to finish this financial year £1.056m under budget. Most of the money comes from interest on the cash it holds, not from cutting services.

The forecast is in a half-year finance report to the council’s Corporate Overview Group, which meets at 7pm on Tuesday 17 November at Rushcliffe Arena. (Financial and Performance Management report; meeting papers)

The council’s capital programme is also forecast to spend £2.6m less than planned this year. The report says those schemes are being moved into 2027/28.

Where the £1.056m comes from

The biggest items, from the report’s own figures:

Item Effect on the budget
Extra interest on cash and investments £734,000 better
Contingency not needed so far £280,000 better
New glass recycling contract with higher rates per tonne £135,000 better
Renegotiated Toothill School leisure contract £110,000 better
Higher diesel and HVO fuel costs £94,000 worse
Garden waste income below target £79,000 worse
Edwalton Golf Centre £60,000 worse
Vacant Bridgford Hall £45,000 worse

The report says interest rates have stayed high, at 3.75%, so the council keeps earning on its cash. It warns that if the council ever needed to borrow, the same rates would hurt.

Where the money would go

None of the £1.056m is left unallocated. The report proposes putting it into reserves.

Bar chart of Rushcliffe Borough Council's proposed allocations of its 2026/27 underspend, in thousands of pounds: local government reorganisation reserve 590, town improvements reserve 300, Greater Nottingham Strategic Plan carry forward 150, new Building Control reserve 133, planning appeals reserve 105, West Bridgford town council review 20
Proposed allocations from the 2026/27 underspend. Chart by West Bridgford Live. Source: Rushcliffe Borough Council, Appendix A.
Share this chartFacebookWhatsAppX
  • £590,000 to top up the reserve for local government reorganisation. The council had £1.199m in it on 1 April. It has since taken out £132,000 for extra staff and £5,000 for the first costs of the judicial review.
  • £300,000 to a town improvements reserve.
  • £150,000 carried forward for the Greater Nottingham Strategic Plan, which is now expected to be adopted between January and February 2027.
  • £133,000 to start a Building Control reserve, from Building Safety Levy grant.
  • £105,000 to refill the planning appeals reserve, which paid for work on the Gamston development framework.
  • £20,000 for the review into whether West Bridgford should get its own town council.

The report says the review “will result in additional cost pressure”, including consultation, governance, election and implementation costs. The full cost is not yet known.

Garden waste and other pressures

Garden waste income is forecast at £1.86m against a budget of £1.939m. The report says it is “unlikely that this will recover”, and blames lower garden waste tonnage. The long dry summer also cut the green waste collected, which pushed the borough’s recycling rate to 46.4%, just under its 47% target.

The council’s savings plan is behind too. It aimed for £278,000 of savings by now and has made £184,000. Garden waste and the home alarms scheme, which has fewer users than expected, account for the gap.

The good news in the figures

  • Car parks: 609,900 users in the half year, over 67,000 more than a year earlier. Income rose by over £56,000 to £692,874. The report reads this as more people using local shops.
  • Affordable homes: 147 delivered against a target of 80 for the period. The full-year target is 160.
  • Council tax: 56.70% collected by the end of September, against 56.99% a year earlier.

What it means for you

An underspend does not change this year’s council tax bill. It goes into reserves. Next year’s council tax is set by Full Council when it agrees the 2027/28 budget.

The Corporate Overview Group is a scrutiny meeting. It can question the figures but does not make the final decision.