National Highways plans no A52 lane closures at Nottingham Knight or Wheatcroft in December. A lane at Nottingham Knight then closes for about four months from early January 2027.
National Highways is not planning any lane closures at the A52’s Nottingham Knight or Wheatcroft junctions in December. Before that, there is one more week of overnight work at Nottingham Knight, from Monday 23 to Friday 27 November.
The pause is short. From the week of 4 January 2027, a lane at Nottingham Knight closes for around four months while utility pipes and cables are moved.
The dates are in an update National Highways added to its A52 Nottingham junctions scheme page on Friday 13 November.
Overview
- This week, to Friday 20 November: lane closures and temporary traffic lights on the A606 at Wheatcroft.
- Sunday 22 November, 7am to 7pm: Flawforth Lane is closed where it joins the A52.
- Monday 23 to Friday 27 November, 8pm to 6am: overnight traffic management on the A52 eastbound at Nottingham Knight.
- December: no planned lane closures at either junction.
- From the week of 4 January 2027: one lane closed at Nottingham Knight for around four months.
- Spring 2027: main construction starts.
What has changed since last week
National Highways’ previous update, dated 5 November, said the Wheatcroft lane closures would stay until “the end of November”. It also said Nottingham Knight would get a week of lane closures in December, with no dates given.
The new update brings both forward and puts times on them:
| Work | 5 November update | 13 November update |
|---|---|---|
| Wheatcroft lane closures end | By the end of November | By Friday 20 November |
| Week of work at Nottingham Knight | One week in December, no dates | Monday 23 to Friday 27 November, overnight 8pm to 6am |
| Lane closures in December | None after the Nottingham Knight week | None planned |
| Nottingham Knight utility work | Four months from January 2027 | From the week of 4 January, around four months |
The Nottingham Knight week is overnight only. National Highways says it is “creating an access point for utilities work starting in January 2027, with traffic management on the A52 eastbound leaving the junction.”
For December it says: “We’re not planning any lane closures at either junction in December. You may still see us working away from the road.”
The four months from January
The January work is the job that was first due to start this month. National Highways moved it, it said on 5 November, “so it didn’t overlap with activities at Wheatcroft”.
In the new update it says: “We’ll close a lane at Nottingham Knight from the week of 4 January, for around four months. We’ll be moving pipes and cables for utilities. We’ll tell you about any road closures before they happen.”
Four months from the week of 4 January takes the work to around the start of May. National Highways has not given an end date.
It has explained why the lanes stay shut overnight and at weekends during this kind of work. Some of it “needs trenches and holes that have to stay open”, so “We can’t safely put up and take down traffic management every morning and evening.”
After that: main construction
Main construction starts in spring 2027. National Highways is turning both roundabouts into through-abouts, which let A52 traffic go straight through the junction.
Its 5 November update said the current lane closures “won’t stay in place until the scheme finishes in 2029”. For the main build, it said, “We’ll aim to keep all lanes open during the main construction phase as much as possible, which should mean less congestion.”
National Highways said on 5 November that its work at Nottingham Knight “has caused a lot of congestion in the area”. NCT reported severe bus delays, and a petition against the closures passed 4,900 signatures in about a day, as we reported on 5 November.
What it means for you
- If you drive the A52 in the evening, expect traffic management on the eastbound side at Nottingham Knight from 8pm to 6am, Monday 23 to Friday 27 November.
- If you use the A606 Melton Road, the Wheatcroft lights should be gone after Friday 20 November.
- If you use Flawforth Lane, it is shut where it joins the A52 from 7am to 7pm on Sunday 22 November, with a signed diversion.
- December journeys, including Christmas shopping trips, should be clear of planned lane closures at both junctions.
- From the week of 4 January, plan for one lane closed at Nottingham Knight for around four months.
National Highways says closures “can change at short notice”. Its daily closures page has the latest, and the other works in town are on our West Bridgford roadworks page.